10-Business Day Main Street Road Closure
Heber to 7th Street - for Kimball Garage Project

Greetings,
With few open spans of time before the weather closes in for the winter and the need for the Kimball Garage project to tie into sewer, water and storm drain, Main Street will be closed between Heber Avenue and 7th street beginning  Monday, September 18 through Friday, September 29 (EXCLUDING THE WEEKEND).  That includes 10 business days. We initially thought it could be done with a partial road closure, but it needs to be full.
 
Here are a few items of note:
  • Road will reopen on the weekend
  • Heber will remain open
  • 7th Street will remain open
  • Main street will remain open above Heber and below 7th Street.
  • There will be signage both high and low on Main Street to divert traffic
  • Sidewalks will remain open on the near Keller Williams and Bahnof Sports
  • Sidewalks on the East side will remain open
  • There will be additional work the first week of October but this will include partial road closures on Heber Avenue, I will update as I get the information.
If you have any questions, please email (best) or call me at 435-615-5206.  I will do my best to keep you updated.
 
Lynn
 
Lynn Ware Peek
Community Engagement Liaison
Park City Municipal Corporation
435-615-5206