Construction

Questar Gas

Questar anticipates completing tying in the businesses, up to Swede Alley, but June 1st.  They will continue uphill and will complete the work up to the Trolley Turn-around by June 15th.  This is Questar's last section on Main Street.

City Hall Plaza

Miller Paving has begun setting brick pavers. They will start the section in front of Liquor Store the week of May 26th. The west corners of Swede Alley and 5th Street will be constructed the first part of June.   During that time they will construct the north-south crosswalk on the west side of Swede Alley.

The City Hall Plaza will be open for the 4th of July weekend.  If the crosswalks are incomplete at that time Miller Paving will return at a later date to complete the crosswalks.

View the construction from the top of China Bridge.  It provides the best perspective of the work.

Main Street Sidewalk Enhancements

May 26 – June 19

Construction will continue on the west side of Main Street from 5th Street to 4th Street.  The storm drain will be complete up to Dugins West.

Miller Paving is striving to finish the majority of this section between 5th Street and Miners Plaza before Savor the Summit.

June 22 – July 3

Miller Paving will set the storm drain, demo the planters along the street at Miners Park, and pour concrete in the sidewalk area at Miners Plaza. Miners Plaza will be improved in a future year, at this time the planters need to be removed to facilitate the storm drain installation.  Any incomplete work in the area will be complete so as to be ready for July 4th weekend.

May 4th

Questar Gas will begin tieing in the individual businesses, between 4th Street and the Wasatch Brew Pub, to the new gas line.

May 11th

Phase 1 of sidewalk construction will begin.  The first section is from the Egyptian Theatre to south end of Cisero’s.  The completion of this section is planned for the end of May.

Mobile Recycling Center

Mondays and Fridays - First Wednesday Service on July 1

  • Uptown Fare, 9:55 -10:05 am
  • The Egyptian, 10:05-10:25 am
  • Bistro 412, 10:25-10:35 am
  • Shabu, 10:35-1045 am
  • Pizza Noodle, 10:45-11 am
  • Yuki Yama, 11-11:15 a
  • Silver Queen Hotel, 11:15-11:30
  • Collie’s, 11:30-11:40 am
  • Butcher’s, 7th Street 11:40-12 noon

New Businesses

No new businesses have moved to the street this month. To see the listing from March click here.