Construction of the 2014 Infrastructure Improvements continue in May.  A tentative schedule is provided below.

May 5th – 17th

  •          Continue work at west side intersection of 7th and Main Street
  •          Pour rat slabs, set pavers middle section – 7th and Main Street
  •          Questar – Begin work on laterals for west side 4th to 5th St. from east side main line
  •          Set curb, pour bands west side Heber to 6th St.
  •          Begin setting pavers west side Heber Ave. to 6th St.

 

May 19th – 30th

  •          Begin work on east side of intersection 7th and Main Street
  •          Continue setting pavers west side Heber Ave to 6th St.
  •          Questar – complete lateral replacement west side 4th to 5th St. 
  •          Questar – complete gas main line tie in at Heber Ave. 

 

Special Considerations:

  •          7th Sl. remains closed to through traffic
  •          Major infrastructure encountered Heber Ave to 6th St.
  •          Businesses will remain open with temporary walkways Heber to 6th
  •          To finish gas main line tie in at Heber Ave need to wait until boardwalk is moved

 

Milestones:

  •          Questar – finished replacing gas laterals east side Heber Ave. to 5th St. 
  •          Completed pavers on west side of intersection 7th and Main Street

 

For further information please contact Craig Sanchez csanchez@parkcity.org 435-615-5206