Main Street Water Line Improvement Project Updates Image

Main Street Water Line Improvement Project Updates

Project Update: Monday, May 13, 2025

Crews continue to make progress replacing fire lines and water service lines to individual properties as Phase III of the Main Street Water Line replacement project. The specific areas crews are working include:

  • Main Street building numbers 368-350, 333 and 361 were completed last week

  • Yesterday, May 12, crews began working on Main Street, building numbers 324 south to Brew Pub Lot

  • May 21-22: crews expect to begin milling and patch paving project trenches

What to Expect:

  • Main Street building numbers 368-350, 333 and 361 were completed last week

  • Yesterday, May 12, crews began working on Main Street building numbers 324 south to Brew Pub Lot

  • May 21-22: crews expect to begin milling and patch paving project trenches

  • During Phase III crews will tie-in individual water service and fire lines. The individual tie-ins are more detailed, invasive, and time-intensive than the installation of the main line

  • Construction equipment and other supplies will be stored securely on the shoulders of Main Street at night and in the Brew Pub Lot

  • Noise from machinery

  • Crews may need access into businesses periodically

  • Old Town parking will remain free throughout the duration of the project (except during special events)

Main Street from 5th to 4th Street:

  • April 7-May 1, 2025, Work Zone | 5th Street to 4th Street:

  • Main Street, from 5th Street to 4th Street – the project area – will be closed during work hours. This area will reopen after project hours to traffic and parking

  • Delivery trucks will be able to enter the project area from both directions

  • Sidewalk closures will be in place, pedestrians will be directed to the opposite side of the street from work being performed. Business access on the closed side of roadway will be accessible by crossing street at the business location

  • Main Street, between Heber Avenue and 5th Street: open to two-way travel

  • Top of Main, between 4th Street and Swede Alley: open to two-way travel

  • 5th Street (by the Post Office) will be switched to one-way heading east for one month

For additional project details, maps of detour routes, and updates, they are available here.

Project Contact:
Park City Municipal
mainstreetwater@parkcity.org | 435- 615-5394 

Main Street Business Contact:
Historic Park City Alliance | Executive Director, Ginger Wicks
ginger@historicparkcityutah.com

Free Parking
Main Street Water Line Improvement Project Updates Image